Contents
Executive Summary
1.1 Background
1.2 Project Description
1.3 Scope of the EM&A Report
1.4 Project Organisation
1.5 Summary of Construction Works
1.6 Summary of EM&A Programme Requirements
1.7 Status of Statutory Environmental Compliance with the Environmental Permit
1.8 Status of Other Statutory Environmental Requirements
2.1 Air Quality Monitoring
2.2 Noise Monitoring
2.3 Water Quality Monitoring
2.4 Landfill Gas Monitoring
2.5 Landscape and Visual Monitoring
2.6 EM&A Site Inspection
2.7 Waste Management Status
2.8 Implementation Status of Environmental Mitigation Measures
2.9 Summary of Exceedances of the Environmental Quality Performance Limit
2.10 Summary of Complaints, Notification of Summons and Successful Prosecutions
3.1 Construction Programme for the Coming Month
3.2 Key Issues for the Coming Month
3.3 Monitoring Schedule for the Coming Month
4 Conclusion and Recommendation
Annexes
Annex B Environmental Mitigation Implementation Schedule
Annex C Monitoring Schedule for This Reporting Period
Annex D Air Quality
Annex D1 Calibration
Certificates for Dust Monitoring Equipment
Annex D2 24-hour
TSP Monitoring Results
Annex D3 Event
and Action Plan for Air Quality Monitoring
Annex D4 Meteorological
Data
Annex D5 Certificates of the Qualified Odour Panelist
Annex D6 Odour Monitoring Results
Annex E Noise
Annex E1 Calibration
Certificates for Noise Monitoring Equipment
Annex E2 Noise
Monitoring Results
Annex E3 Event
and Action Plan for Noise Monitoring
Annex F Water Quality
Annex F1 Calibration
Certificates for Surface Water Quality Monitoring Equipment
Annex F2 Surface
Water Quality Monitoring Results
Annex F3 Event
and Action Plan for Water
Quality Monitoring
Annex F4 Calibration Certificates for Effluent Quality Monitoring Equipment
Annex F5 Leachate Levels Monitoring Results
Annex F6 Effluent Quality Monitoring Results
Annex F7 Calibration Certificates for Groundwater Monitoring Equipment
Annex F8 Groundwater Monitoring Results
Annex F9 Investigation Reports of Environmental Quality Limit Exceedance
Annex G Landfill Gas
Annex G1 Landfill
Gas Monitoring Locations for Service Voids, Utilities and Manholes Along the
Site Boundary and Within the SENTX Site
Annex G2 Calibration Certificates for Landfill Gas Monitoring
Equipment
Annex G3 Landfill
Gas Monitoring Results
Annex G4 Event
and Action Plan for Landfill
Gas Monitoring
Annex I Monitoring Schedule for the Next Reporting Period
The SENT Landfill Extension (SENTX) forms an integral part in the Strategic Plan in maintaining the continuity of landfill capacity in the Hong Kong for the cost-effective and environmentally satisfactory disposal of waste. ERM-Hong Kong, Limited (ERM) is commissioned to undertake the role of Environmental Team (ET) for the construction, operation/restoration and aftercare of SENTX Project (“the Project”) in accordance with the requirements specified in the Environmental Permit (EP), updated Environmental Monitoring and Audit (EM&A) Manual, the approved Environmental Impact Assessment (EIA) Report of the Project taking account of the latest design and other relevant statutory requirements. The construction (not including works related to site clearance and preparation) and operation of the Project commenced on 2 January 2019 and 21 November 2021, respectively.
This Monthly EM&A report presents the EM&A works carried out during the period from 1 to 31 March 2022 for the Project in accordance with the updated EM&A Manual.
Exceedance of Action and Limit Levels for Air Quality
No exceedance of Action and Limit Levels for operation/ restoration phase air quality monitoring was recorded in the reporting period.
Exceedance of Action and Limit Levels for Noise
No exceedance of Action and Limit Levels for operation/ restoration phase noise monitoring was recorded in the reporting period.
Exceedance of Action and Limit Levels for Water Quality
One exceedance of the Limit Level for groundwater (Chemical Oxygen Demand (COD)) was recorded for water quality impact monitoring in the reporting period. The groundwater (COD) exceedance at MWX-4 on 15 March 2022 was considered non Project-related upon further investigation.
Exceedance of Action and Limit Levels for Landfill Gas
No exceedance of Action and Limit Levels for operation/ restoration phase landfill gas monitoring was recorded in the reporting period.
Environmental Complaints, Summons and Prosecutions
There were no complaints, notification of summons or prosecution recorded in the reporting period.
Reporting Change
There was no reporting change in the reporting period.
Future Key Issues
Potential environmental impacts arising from the upcoming construction/ operational activities in the next reporting period of April 2022 are mainly associated with potential surface water impact in the rainy season.
The SENT Landfill Extension (SENTX) forms an integral part in the Strategic Plan in maintaining the continuity of landfill capacity in the Hong Kong for the cost-effective and environmentally satisfactory disposal of waste. The Environmental Impact Assessment (EIA) Report and the associated Environmental Monitoring and Audit (EM&A) Manual for the construction, operation, restoration and aftercare of the SENTX (hereafter referred to as “the Project”) have been approved under the Environmental Impact Assessment Ordinance (EIAO) in May 2008 (Register No.: AEIAR-117/2008) (hereafter referred to as the approved EIA Report) and an Environmental Permit (EP-308/2008) (EP) was granted by the Director of Environmental Protection (DEP) on 5 August 2008.
Since then, applications for Variation of an Environmental Permit (No. VEP-531/2017) were submitted to EPD and the Variation of Environmental Permits (EP-308/2008/A and EP-308/2008/B) were granted on 6 January 2012 and 20 January 2017, respectively, as the Hong Kong SAR Government has decided to reduce the scale of the design scheme of SENTX assessed in the approved EIA Report and SENTX will only receive construction waste. In May 2018, a Further Environmental Permit (FEP) (FEP-01/308/2008/B) was granted to the SENTX’s contractor, Green Valley Landfill, Limited (GVL).
ERM-Hong Kong, Limited (ERM) and Meinhardt Infrastructure and Environment Limited (Meinhardt) are commissioned to undertake the roles of Environmental Team (ET) and the Independent Environmental Checker (IEC), respectively, to undertake the EM&A activities for the Project in accordance with the requirements specified in the EP, updated EM&A Manual ([1]), approved EIA Report ([2]) taking account of the latest design and other relevant statutory requirements.
The SENTX is a piggyback landfill, occupying the southern part of the existing SENT Landfill (including its infrastructure area) and 13 ha of Tseung Kwan O (TKO) Area 137. A layout plan of the SENTX is shown in Figure 1.1. Under the latest design, the SENTX has a net void capacity of about 6.5 Mm3 and provides an additional lifespan of about 6 years, commencing operation upon exhaustion of the SENT Landfill. The SENTX will receive construction waste only.
The key implementation milestones of the Project are indicatively summarised in Table 1.1. The construction works and operation of the Project commenced on 2 January 2019 and 21 November 2021, respectively.
Table 1.1 Estimated Key Dates of Implementation Programme
Key Stage of the Project |
Indicative Date |
Start construction |
2 January 2019 |
Commissioning of new infrastructure facilities |
2020 |
Demolition of existing infrastructure facilities |
2021 |
Start waste intake at SENTX |
21 November 2021 |
Estimated exhaustion date of SENTX |
2027 |
End of aftercare for SENTX |
2057 |
The major construction works of the SENTX includes:
· Site formation at the TKO Area 137 and the existing infrastructure area at SENT Landfill;
· Construction of surface and groundwater drainage systems;
· Construction of the leachate containment and collection systems;
· Construction of new leachate and landfill gas treatment facilities, site offices, maintenance yards at the new infrastructure area;
· Construction of new pipelines to transfer the leachate and landfill gas collected from the existing SENT Landfill to the treatment facilities at the new infrastructure area;
· Construction of the site access and new waste reception facilities; and
· Demolition of the facilities at the existing SENT Landfill infrastructure area.
This is the Monthly EM&A Report for the Project which summarises the key findings of the EM&A programme during the reporting period from 1 to 31 March 2022 for the construction and operation works.
The organisation structure of the Project is presented in Figure 1.2.
Figure 1.2 Organisation Chart
Contact details of the key personnel are summarised in Table 1.2 below.
Table 1.2 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Contractor (Green Valley Landfill Limited) |
Project Manager |
Carl Lai |
2706 8829 |
Environmental Team (ET) (ERM-Hong Kong, Limited) |
ET Leader |
Frank Wan |
2271 3152 |
Independent Environmental Checker (IEC) (Meinhardt Infrastructure and Environment Limited) |
IEC |
W.K. Chiu |
2858 0738 |
The programme of the construction is shown in Annex A. As informed by the Contractor, the major works carried out in this reporting period include:
· Rectification of defects at Landfill Gas (LFG) Plant, Leachate Treatment Plant (LTP), infrastructure area and waste reception area;
· Landscaping works at infrastructure area;
· Rectification of defects for underground utilities and pipe;
· Construction of MSE wall;
· Construction of retaining wall at Western boundary planting;
· Liner works at Cell 4X;
· Construction of perimeter channel X10A and X10C along Western bund of Cell 4X;
· Maintenance and improvement of temporary surface water drainage; and
· Utilities installation along Western bund of Cell 4X.
The implementation schedule of the mitigation measured recommended in the Updated EM&A Manual is presented in Annex B.
The status for all environmental aspects are presented in Table 1.3. The EM&A requirements remained unchanged during the reporting period.
Table 1.3 Summary of Status for the Environmental Aspects under the Updated EM&A Manual
Parameters |
Status |
Air Quality |
|
Baseline Monitoring |
The results of baseline air quality monitoring were reported in Baseline Monitoring Report and Pre-operation Baseline Monitoring Report and submitted to EPD under EP Condition 3.3 |
Impact Monitoring |
On-going |
Noise |
|
Baseline Monitoring |
The results of baseline noise monitoring were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.3 |
Impact Monitoring |
On-going |
Water Quality |
|
Baseline Monitoring |
The results of baseline surface water quality monitoring were reported in Baseline Monitoring Report and Pre-operation Baseline Monitoring Report and submitted to EPD under EP Condition 3.3 |
Impact Monitoring |
On-going |
Landfill Gas |
|
Impact Monitoring |
On-going |
Waste Management |
|
Waste Monitoring |
On-going |
Landscape and Visual |
|
Baseline Monitoring |
The results of baseline landscape and visual monitoring were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.3 |
Operation Phase Audit |
On-going |
Site Environmental Audit |
|
Regular Site Inspection |
On-going |
Complaint Hotline and Email Channel |
On-going |
Environmental Log Book |
On-going |
Taking into account the operation works, impact monitoring of air quality, noise, water quality, landfill gas and waste management were carried out in the reporting period. The impact monitoring schedule of air quality, noise, water quality and landfill gas monitoring are provided in Annex C.
The EM&A programme also involved environmental site inspections and related auditing conducted by the ET for checking the implementation of the required environmental mitigation measures recommended in the approved EIA Report and relevant EP submissions. To promote the environmental awareness and enhance the environmental performance of the contractors, environmental trainings and regular environmental management meetings were conducted during the reporting period, which are summarised as below:
One environmental management meeting was held with the Contractor, ER, ET, IEC and EPD on 24 March 2022; and
Environmental toolbox trainings on Chemical Waste Handling and Green Procurement were provided on 9 March and 23 March 2022 respectively by the Contractor to the workers.
The status of statutory environmental compliance with the EP conditions under the EIAO, submission status under the EP and implementation status of mitigation measures are presented in Table 1.4.
Table 1.4 Status of Submissions required under the EP and Implementation Status of Mitigation Measures
EP Condition |
Submission / Implementation Status |
Status |
2.3 |
Management Organisation of Main Construction Companies |
Submitted and accepted by EPD. |
2.4 |
Setting up of Community Liaison Group |
Community Liaison Group was set up. |
2.5 |
Submission of Detailed Landfill Gas Hazard Assessment Report |
Submitted and accepted by EPD on 10 January 2019. |
2.6 |
Submission of Restoration and Ecological Enhancement Plan |
Submitted to EPD on 28 June 2019. |
2.7 |
Setting up of Trial Nursery |
Trial Nursery works was commenced on 28 August 2019. |
2.8 |
Advance Screen Planting |
Advance Screen Planting works were completed on 28 June 2019. |
2.9 |
Provision of Multi-layer Composite Liner System |
Under implementation. |
The environmental licenses and permits (including EP, Water Pollution Control Ordinance (WPCO) discharge license, registration as a chemical waste producer, and construction noise permit) that are valid in the reporting period are presented in Table 1.5. No non-compliance with environmental statutory requirements was identified.
Table 1.5 Status of Statutory Environmental Requirements
Description |
Ref No. |
Status |
Environmental Permit |
EP-308/2008 |
Granted on 5 August 2008 |
Variation of Environmental Permit |
EP-308/2008/A |
Granted on 6 January 2012 |
EP-308/2008/B |
Granted on 20 January 2017 |
|
Further Environmental Permit |
FEP-01/308/2008/B |
Granted on 16 May 2018 |
Water Discharge License under WPCO (Permit Holder: GVL) |
Licence No.: WT00036269-2020 |
Validity from 21 June 2020 to 30 June 2022 |
Billing Account for Disposal of Construction Waste |
Chit Account Number: 5001692 |
Approved on 28 December 2005 |
Registration as a Chemical Waste Producer (Permit Holder: Chun Wo) |
5213-839-C3507-10 |
Issued on 23 August 2018 |
Registration as a Chemical Waste Producer (Permit Holder: REC) |
5518-839-R2289-06 |
Issued on 24 October 2019 |
Construction Noise Permit (Permit Holder: GVL) |
GW-RE1316-21 |
Validity from 5 January 2022 to 14 June 2022 |
Construction Noise Permit (Permit Holder: Paul Y.) |
GW-RE0278-22 |
Validity from 31 March 2022 to 22 September 2022 |
The EM&A programme for the Project required environmental monitoring for air quality, noise, water quality and landfill gas as well as environmental site inspections for air quality, noise, water quality, landfill gas, waste management, and landscape and visual impacts. The EM&A requirements and related findings for each component are summarised in the following sections.
According to the updated EM&A Manual of the Project, impact dust monitoring (in term of Total Suspended Particulates (TSP)) was carried out at the four designated locations along the site boundary (i.e. AM1, AM2, AM3 and AM4) during the operation/restoration phase, at a 6-day interval.
The Action and Limit Levels of the dust monitoring is provided in Table 2.1 below.
Table 2.1 Action and Limit Levels for 24-hour TSP
Monitoring Station |
Action Level |
Limit Level |
AM1 - SENTX Site Boundary (North) |
260 µg m-³ |
260 µg m-³ |
AM2 - SENTX Site Boundary (West, near DP3) |
||
AM3 - SENTX Site Boundary (West, near RC15) |
||
AM4 - SENTX Site Boundary (West, near EPD building) |
High volume air samplers (HVSs) in compliance with the specifications listed under Section 3.2.2 of the updated EM&A Manual were used to measure 24-hour TSP levels at the dust monitoring stations. The HVSs were calibrated upon installation and thereafter at bi-monthly intervals to check the validity and accuracy of the results.
The equipment used in the impact dust monitoring programme and monitoring locations are summarised in Table 2.2 and illustrated in Figure 2.1, respectively. Copies of the calibration certificates for the equipment are presented in Annex D1.
Table 2.2 Dust Monitoring Details
Monitoring Station |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
AM1 |
SENTX Site Boundary (North) |
24-hour TSP |
Once every 6 days |
1, 7, 13, 19, 25, 31 Mar 2022 |
Tisch TE-5170 (S/N: 1190) |
AM2 |
SENTX Site Boundary (West, near DP3) |
Tisch TE-5170 (S/N: 1047) |
|||
AM3 |
SENTX Site Boundary (West, near RC15) |
Tisch TE-5170 (S/N: 1258) |
|||
AM4 |
SENTX Site Boundary (West, near EPD building) |
Tisch TE-5170 (S/N: 1101) |
The schedule for dust monitoring during the reporting period is provided in Annex C.
The monitoring results for 24-hour TSP are summarised in Table 2.3. The detailed monitoring results and the graphical presentation of the 24-hour TSP results at each monitoring location are provided in Annex D2.
Table 2.3 Summary of 24-hour TSP Monitoring Results in the Reporting Period
Monitoring Station |
Average 24-hr TSP Concentration (µg m-3) (Range in bracket) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
AM1 - SENTX Site Boundary (North) |
96 (62 – 133) |
260 |
260 |
AM2 - SENTX Site Boundary (West, near DP3) |
70 (39 – 106) |
260 |
260 |
AM3 - SENTX Site Boundary (West, near RC15) |
163 (35 – 224) |
260 |
260 |
AM4 - SENTX Site Boundary (West, near EPD building) |
81 (33 – 107) |
260 |
260 |
The major dust sources in the reporting period included fugitive dust emission from exposed area in SENTX, as well as nearby operations of the SENTX and the TKO Area 137 Fill Bank.
All the 24-hour TSP results were below the Action and Limit Levels at the monitoring locations in the reporting period. No action is thus required to be undertaken in accordance with the Event and Action Plan presented in Annex D3.
Meteorological data obtained from the SENTX on-site meteorological monitoring station was used for the dust monitoring and is shown in Annex D4. It is considered that meteorological data obtained at the on-site meteorological monitoring station is representative of the Project area and could be used for the operation/restoration phase dust monitoring programme for the Project.
According to the updated EM&A Manual of the Project, odour patrol was carried out along the site boundary during the operation/ restoration phase. During the first month of operation, daily odour patrol (3 times per day) was conducted jointly by the ET and the IEC. The odour intensity detected was based on that determined by the IEC. In addition, an independent party (ALS Technichem (HK) Pty Ltd.) was appointed to undertake odour patrol together with the ET and IEC three times per week. During these patrols, the odour intensity detected was based on that determined by the independent third party.
Reduction of odour monitoring frequency from Period 1 (daily, three times per day) to Period 2 (weekly)) was approved by EPD on 4 February 2022. Weekly odour patrol was conducted jointly by the ET and the IEC from 4 February 2022. In addition, an independent party (ALS Technichem (HK) Pty Ltd.) was appointed to undertake odour patrol together with the ET and IEC once every two weeks.
The Action and Limit Levels for odour patrol is provided in Table 2.4 below.
Table 2.4 Action and Limit Levels for Odour Patrol
Parameter |
Action Level |
Limit Level |
Perceived odour intensity and odour complaints |
· Odour intensity ≥ Class 2 recorded; or · One documented complaint received |
· Odour intensity ≥ Class 3 recorded on 2 consecutive patrol (a) (b)
|
Notes: (a) i.e. either Class 3-strong or Class 4-extreme odour intensity. (b) The exceedances of the odour intensity do not need to be recorded at the same location. |
Odour patrol was conducted by trained personnel / competent persons with a specific sensitivity to a reference odour (i.e. on reference materials n-butanol with the concentration of 50ppm in nitrogen (v/v)) in compliance with Section 3.7.2 of the updated EM&A Manual patrolling and sniffing along the SENTX Site boundary to detect any odour.
The odour monitoring programme and patrol route are summarised in Table 2.5 and illustrated in Figure 2.2 respectively. Copies of the certificates of the qualified odour panelist are presented in Annex D5.
Table 2.5 Odour Monitoring Details
Patrol Locations |
Parameters |
Patrol Frequency (a) |
Monitoring Dates |
Patrol along the SENTX Site Boundary (Checkpoints OP1 – OP11) |
Odour Intensity (see Table 2.6) |
Period 1 - First month of operation Daily, three times a day in the morning, afternoon and evening/night (between 18:00 and 22:00 hrs) conducted by the ET and the IEC
Three times per week on different days conducted by an independent third party together with the ET and IEC (b)
Period 2 - Three months following period 1 (c)
Weekly conducted by the ET and the IEC
Once every two weeks conducted by an independent third party together with the ET and IEC (b)
Period 3 - Throughout operation following period 2 (c) Monthly conducted by the ET and the IEC
Quarterly conducted by an independent third party together with the ET and IEC (b) |
Conducted by ET & IEC: 7, 16, 21, 29 Mar 2022
Conducted by an independent third party, ET & IEC: 7, 21 Mar 2022 |
Notes: (a) Reduction of monitoring frequency will be subject to the monitoring results to demonstrate environmentally acceptable performance. (b) Patrol shall be scheduled so that they are carried out together with the patrols to be carried out jointly by the ET and the IEC. (c) Commencement of each period will be justified by the ET Leader and verified by the IEC and will be subject to agreement with the EPD (EIAO Authority) and Project Proponent. |
Table 2.6 Odour Intensity Level
Class |
Odour Intensity |
Description |
0 |
Not Detected |
No odour perceived or an odour so weak that it cannot be easily characterised or described. |
1 |
Slight |
Identified odour, slight |
2 |
Moderate |
Identified odour, moderate |
3 |
Strong |
Identified odour, strong |
4 |
Extreme |
Severe odour |
The schedule for odour patrol during the reporting period is provided in Annex C.
The odour monitoring results are summarised and provided in Table 2.7 and Annex D6, respectively.
Table 2.7 Summary of Odour Monitoring Results in the Reporting Period
Odour Checkpoints |
Odour Intensity Class (Range) |
Action Level |
Limit Level |
OP1 |
0 |
Odour intensity ≥ Class 2 recorded |
Odour intensity ≥ Class 3 recorded on 2 consecutive patrol |
OP2 |
0 |
||
OP3 |
0 |
||
OP4 |
0 |
||
OP5 |
0 |
||
OP6 |
0 |
||
OP7 |
0 – 1 |
||
OP8 |
0 – 1 |
||
OP9 |
0 |
||
OP10 |
0 |
||
OP11 |
0 – 1 |
|
|
The potential odour sources in the reporting period included the slurry truck, excavator as well as the operation of generator at SENTX.
All the odour monitoring results were below the Action and Limit Levels in the reporting period. No action is thus required to be undertaken in accordance with the Event and Action Plan presented in Annex D3.
According to the updated EM&A Manual of the Project, the performance of the thermal oxidiser, landfill gas flare and landfill gas generator was monitored when they are in operation. Gas samples were collected from the stack of the thermal oxidizer, landfill gas flare and landfill gas generator for laboratory analysis for NO2, CO, SO2, Benzene and Vinyl chloride and in-situ analysis for exhaust gas velocity at monthly interval. The operating conditions of the thermal oxidiser, landfill gas flare and landfill gas generator were also monitored continuously.
The Limit Levels for stack emission of the thermal oxidiser, landfill gas flare and landfill gas generator are provided in Tables 2.8 – 2.10 below.
Table 2.8 Limit Levels for Stack Emission of the Thermal Oxidiser
Parameters |
Limit Level |
NO2 |
1.58 gs-1 |
CO |
0.53 gs-1 |
SO2 |
0.07 gs-1 |
Benzene |
3.01 x 10-2 gs-1 |
Vinyl chloride |
2.23 x 10-3 gs-1 |
Gas combustion temperature |
850oC (minimum) |
Exhaust gas exit temperature |
443K (minimum) (a) |
Exhaust gas velocity |
7.5 ms-1 (minimum) (a) |
Note: (a) Level under full load condition. |
|
Table 2.9 Limit Levels for Stack Emission of the Landfill Gas Flare
Parameters |
Limit Level |
NO2 |
0.97 gs-1 |
CO |
2.43 gs-1 |
SO2 |
0.22 gs-1 |
Benzene |
4.14 x 10-4 gs-1 |
Vinyl Chloride |
2.60 x 10-4 gs-1 |
Gas combustion temperature |
815oC (minimum) |
Exhaust gas exit temperature |
923 K (minimum) (a) |
Exhaust gas velocity |
9.0 m s-1 (minimum) (a) |
Note: (a) Level under full load condition. |
|
Table 2.10 Limit Levels for Stack Emission of the Landfill Gas Generator
Parameters |
Limit Level |
NO2 |
1.91 gs-1 |
CO |
2.48 gs-1 |
SO2 |
0.528 gs-1 |
Benzene |
2.47 x 10-4 gs-1 |
Vinyl chloride |
1.88 x 10-5 gs-1 |
Gas combustion temperature |
450oC (minimum) |
Exhaust gas exit temperature |
723K (minimum) (a) |
Exhaust gas velocity |
30.0 ms-1 (minimum) (a) |
Note: (a) Level under full load condition. |
|
Gas samples were collected from the centroid of the stack with stainless steel sampling probe, into inert sample containers (i.e. Canister and Tedlar Bag) and transferred to ALS Technichem (HK) Pty Ltd. (HOKLAS Registration No. 066) laboratory within 24 hours of collection for direct analysis on a gas chromatography within 48 hours after collection. The flue gas velocity of the gas stream at the exhaust of thermal oxidize was determined by S-Pitot tube during the emission sampling.
The stack emission monitoring programme and monitoring locations are summarised in Table 2.11 and illustrated in Figure 2.1, respectively.
Table 2.11 Thermal Oxidiser, Landfill Gas Flare and Landfill Gas Generator Stack Emission Monitoring Details
Monitoring Location |
Parameter |
Frequency |
Monitoring Date |
Stack of Thermal Oxidiser |
Laboratory analysis for · NO2 · CO · SO2 · Benzene · Vinyl chloride In-situ analysis for · Exhaust gas velocity |
Monthly for the first 12 months of operation and thereafter at quarterly intervals |
7 Mar 2022 |
· Gas combustion temperature · Exhaust temperature · Exhaust gas velocity (a) |
Continuously |
1 – 31 Mar 2022 |
|
Stack of Landfill Gas Flare |
Laboratory analysis for · NO2 · CO · SO2 · Benzene · Vinyl chloride In-situ analysis for · Exhaust gas velocity |
Monthly for the first 12 months of operation and thereafter at quarterly intervals |
8 Mar 2022 |
· Gas combustion temperature · Exhaust temperature · Exhaust gas velocity (a) |
Continuously |
1 – 31 Mar 2022 |
|
Stack of Landfill Gas Generator |
Laboratory analysis for · NO2 · CO · SO2 · Benzene · Vinyl chloride In-situ analysis for · Exhaust gas velocity |
Monthly for the first 12 months of operation and thereafter at quarterly intervals |
8 Mar 2022 |
· Exhaust temperature · Exhaust gas velocity (a) |
Continuously |
1 – 31 Mar 2022 |
|
Notes: (a) The exhaust gas velocity is calculated based on the cross-section area of the stack and continuous monitored gas flow and combustion temperature data. (b) The monitoring results will be reviewed towards the end of the first year of operation to determine if monitoring of this parameter can be terminated upon agreement by the EIAO Authority, IEC and Project Proponent. |
The schedule for thermal oxidizer, landfill gas flare and landfill gas generator stack emission monitoring during the reporting period is provided in Annex C.
The thermal oxidizer, landfill gas flare and landfill gas generator stack emission monitoring results and detailed continuous monitoring results are summarised in Tables 2.12 - 2.14 and provided in Annex D7, respectively.
Table 2.12 Summary of Thermal Oxidiser Stack Emission Monitoring in the Reporting Period
Parameters |
Monitoring Results (Range in Bracket) |
Limit Level |
NO2 |
1.54 gs-1 |
1.58 gs-1 |
CO |
0.04 gs-1 |
0.53 gs-1 |
SO2 |
<0.01 gs-1 |
0.07 gs-1 |
Benzene |
<3 x 10-5 gs-1 |
3.01 x 10-2 gs-1 |
Vinyl chloride |
<3 x 10-5 gs-1 |
2.23 x 10-3 gs-1 |
Gas combustion temperature |
979oC (959oC – 1,035oC) |
850oC (minimum) |
Exhaust gas exit temperature |
957K (941K – 1,003K) |
443K (minimum) (a) |
Exhaust gas velocity |
9.1 ms-1 (b) |
7.5 ms-1 (minimum) (a) |
Notes: (a) Level under full load condition. (b) The exhaust gas velocity was calculated based on the cross-section area of the stack and the gas flow and combustion temperature data measured during the stack emission monitoring. The limit level was not applicable as the stack was not operated under full load condition. |
Table 2.13 Summary of Landfill Gas Flare Stack Emission Monitoring in the Reporting Period
Parameters |
Monitoring Results (Range in Bracket) |
Limit Level |
NO2 |
0.02 gs-1 |
0.97 gs-1 |
CO |
0.056 gs-1 |
2.43 gs-1 |
SO2 |
0.007 gs-1 |
0.22 gs-1 |
Benzene |
<1.2 x 10-5 gs-1 |
4.14 x 10-4 gs-1 |
Vinyl chloride |
<1.0 x 10-5 gs-1 |
2.60 x 10-4 gs-1 |
Gas combustion temperature |
Flare 1: 911oC (830oC – 990oC) Flare 2: 854oC (820oC – 890oC) |
815oC (minimum) |
Exhaust gas exit temperature |
Flare 1: 1,141K (1,073K – 1,223K) Flare 2: 1,077K (1,033K – 1,123K) |
923 K (minimum) (a) |
Exhaust gas velocity |
3.9 ms-1 (b) |
9.0 m s-1 (minimum) (a) |
Note: (a) Level under full load condition. (b) The exhaust gas velocity was calculated based on the cross-section area of the stack and the gas flow and combustion temperature data measured during the stack emission monitoring. The limit level was not applicable as the stack was not operated under full load condition. |
Table 2.14 Summary of Landfill Gas Generator Stack Emission Monitoring in the Reporting Period
Parameters |
Monitoring Results (Range in Bracket) |
Limit Level |
NO2 |
0.022 gs-1 |
1.91 gs-1 |
CO |
0.06 gs-1 |
2.48 gs-1 |
SO2 |
<0.001 gs-1 |
0.528 gs-1 |
Benzene |
<2 x 10-6 gs-1 |
2.47 x 10-4 gs-1 |
Vinyl chloride |
<1.9 x 10-6 gs-1 |
1.88 x 10-5 gs-1 |
Exhaust gas exit temperature |
845K (840K – 850K) |
723K (minimum) (a) |
Exhaust gas velocity |
7.8 ms-1 (b) |
30.0 ms-1 (minimum) (a) |
Note: (a) Level under full load condition. (b) The exhaust gas velocity was calculated based on the cross-section area of the stack and the gas flow and combustion temperature data measured during the stack emission monitoring. The limit level was not applicable as the stack was not operated under full load condition. |
All thermal oxidizer, landfill gas flare and landfill gas generator stack emission monitoring results were below the Limit Levels in the reporting period. No action is thus required to be undertaken in accordance with the Event and Action Plan presented in Annex D3.
According to the updated EM&A Manual of the Project, impact noise monitoring was conducted weekly at the monitoring location (i.e. NM1) to obtain one set of 30 minutes measurement between 07:00 and 19:00 hours on normal weekdays.
The Action and Limit Levels for operational noise of the Project are provided in Table 2.15 below.
Table 2.15 Action and Limit Levels for Operational Noise
Time Period |
Action Level (a) |
Limit Level (b) |
07:00 – 19:00 hrs on all days
|
When one documented complaint is received from any one of the noise sensitive receivers (NSRs) or 75 dB(A) recorded at the monitoring station |
65 dB(A) at NSRs (c) |
19:00 – 23:00 hrs on all days
|
65 dB(A) at NSRs (c) |
|
23:00 – 07:00 hrs on all days |
55 dB(A) at NSRs (c) |
|
Notes: (a) 75dB(A) along and at about 100m from the SENTX site boundary was set as the Action Level. (b) Limits specified in the GW-TM and IND-TM for construction and operational noise, respectively. (c) Limit Level only apply to operational noise without road traffic and construction activities noise. |
Noise monitoring was performed by ALS Technichem (HK) Pty Ltd. (HOKLAS Registration No. 066) using sound level meter at the designated monitoring station NM1 (see Figure 2.1) in accordance with the requirements stipulated in the updated EM&A Manual. Acoustic calibrator was deployed to check the sound level meter at a known sound pressure level. Details of the deployed equipment are provided in Table 2.16. Copies of the calibration certificates for the equipment are presented in Annex E1.
Table 2.16 Noise Monitoring Details
Monitoring Station (1) |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
NM1 |
SENTX Site Boundary (North) |
Leq (30 min) measurement between 07:00 and 19:00 hours on normal weekdays (Monday to Saturday) |
Once per week for 30 mins during operation of the Project |
2, 8, 14, 21, 28 Mar 2022 |
Sound Level Meter: Rion NL-52 (S/N: 00921191)
Acoustic Calibrator: Rion NC-74 (S/N: 34246492)
|
The schedule for noise monitoring during the reporting period is provided in Annex C.
A total of 5 impact noise monitoring events were scheduled during the reporting period. However, noise monitoring on 28 March 2022 was cancelled due to adverse weather condition. Results for noise monitoring are summarised in Table 2.17. The monitoring results and the graphical presentation of the data are provided in Annex E2.
Table 2.17 Summary of Operation Noise Monitoring Results in the Reporting Period
Monitoring Station |
Measured Noise Level Leq (30 min), dB(A) |
||
Average |
Range |
Action and Limit Level |
|
NM1 |
48.6 |
45.9 – 51.3 |
75 |
Major noise sources identified during the noise monitoring included noise from operations of the SENTX and the TKO Area 137 Fill Bank, aircrafts and insects.
No Action and Limit Levels exceedance was recorded for operation noise monitoring in the reporting period. No action is thus required to be undertaken in accordance with the Event and Action Plan presented in Annex E3.
According to the updated EM&A Manual of the Project, impact surface water quality monitoring was carried out at the three designated surface water discharge points (i.e. DP3, DP4 and DP6) at monthly intervals during operation/ restoration phase to ensure that the SENTX will not cause adverse water quality impact. Suspension of impact surface water quality monitoring at DP3 was approved under the Baseline Monitoring Report by EPD on 24 July 2019 until the actual commencement of construction works affecting DP3 in 2022.
The parameters as listed in Table 2.19 were determined by ALS Technichem (HK) Pty Ltd. (HOKLAS Registration No. 066).
The Limit Levels of the surface water quality impact monitoring are provided in Table 2.18.
Table 2.18 Limit Levels for Surface Water Quality
Parameters |
Limit Level |
DP4 & DP6 |
|
Ammoniacal-nitrogen |
> 7.1 mg/L |
COD |
> 30 mg/L |
SS |
> 20 mg/L |
The locations of the monitoring stations for the Project are shown in Figure 2.1. All in situ monitoring instruments were checked, calibrated and certified by a laboratory accredited under HOKLAS or other international accreditation scheme before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the surface water quality monitoring programme. Calibration for a DO meter was carried out before measurement according to the instruction manual of the equipment model. Details of the equipment used in the impact surface water quality monitoring works are provided in Table 2.19. Copies of the calibration certificates for the equipment are presented in Annex F1.
Table 2.19 Impact Surface Water Quality Monitoring Details
Monitoring Station |
Location |
Frequency |
Monitoring Dates |
Parameter |
Equipment |
|
DP4 |
Surface water discharge point DP4 |
Monthly |
21 Mar 2022 |
· pH · Electrical conductivity (EC) · DO · SS · COD · BOD5 · TOC · Ammoniacal–nitrogen · Nitrate-nitrogen · Nitrite–nitrogen · TKN · TN · Phosphate · Sulphate · Sulphide · Carbonate · Oil & Grease
|
· Bicarbonate · Chloride · Sodium · Potassium · Calcium · Magnesium · Nickel · Manganese · Chromium · Cadmium · Copper · Lead · Iron · Zinc · Mercury · Boron
|
YSI Professional DSS (S/N: 15H103928)
|
DP6 |
Surface water discharge point DP6 |
|||||
Notes: (a) Impact surface water quality monitoring at DP3 was suspended from the monitoring event on 25 July 2019 until the actual commencement of construction works affecting DP3 in 2022. |
The schedule for surface water quality monitoring during the reporting period is provided in Annex C.
One monitoring event for impact surface water quality monitoring was scheduled at all designated monitoring stations during the reporting period. However, sampling could not be carried out on 21 March 2022 due to insufficient flow. Details of impact water quality monitoring event are provided in Annex F2.
No action is thus required to be undertaken in accordance with the Event and Action Plan presented in Annex F3.
According to the updated EM&A Manual, continuous monitoring of leachate level and daily monitoring of effluent quality were carried out during the operation/ restoration phase.
Reduction of effluent monitoring frequency (dry season) (from daily to monthly) was approved by EPD on 22 March 2022. Monthly effluent quality monitoring (dry season) shall be conducted from 23 March 2022.
Temperature, pH and volume of the effluent discharged from the leachate treatment plant were measured in-situ whereas the parameters as listed in Table 2.21 were determined by ALS Technichem (HK) Pty Ltd. (HOKLAS Registration No. 066).
The Limit Levels of the leachate monitoring are provided in Table 2.20.
Table 2.20 Limit Levels for Leachate Levels and Effluent Quality
Parameters |
Limit Level |
Leachate Levels |
|
Leachate levels above the basal liner |
1 m above the primary liner of the leachate containment system |
Effluent Quality |
|
Temperature |
> 43 °C |
pH Value |
6 – 10 |
Volume Discharged |
>1,500 m³ |
Suspended Solids (SS) |
> 800 mg/L |
Phosphate |
> 25 mg/L |
Sulphate |
> 900 mg/L |
Total Inorganic Nitrogen (a) |
> 100 mg/L |
Biochemical Oxygen Demand (BOD) |
> 800 mg/L |
Chemical Oxygen Demand (COD) |
> 2,000 mg/L |
Oil & Grease |
> 20 mg/L |
Boron |
> 7,000 µg/L |
Iron |
> 7.5 mg/L |
Cadmium |
> 1 µg/L |
Chromium |
> 400 µg/L |
Copper |
> 1,000 µg/L |
Nickel |
> 800 µg/L |
Zinc |
> 800 µg/L |
Note: (a) Total Inorganic Nitrogen include Ammoniacal-nitrogen, Nitrite-nitrogen and Nitrate-nitrogen. |
All in situ monitoring instruments were checked, calibrated and certified by a laboratory accredited under HOKLAS or other international accreditation scheme before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the leachate quality monitoring programme. Details of the equipment used are provided in Table 2.21. Copies of the calibration certificates for the equipment are presented in Annex F4.
Table 2.21 Leachate Levels and Effluent Quality Monitoring Details
Location |
Frequency |
Parameter |
Monitoring Dates |
Equipment |
Leachate levels above the basal liner
|
Continuous |
Leachate Levels |
1 – 31 Mar 2022 |
Pairs of pressure transducers |
Effluent discharged from LTP |
Daily for the first 3 months upon full operation of the LTP at wet season (Apr to Sep) and dry season (Oct to Mar), respectively and reduce to monthly thereafter subject to the monitoring results of the first 3 months for each season and agreement with the EIAO Authority, IEC and IC. (a) |
On-site Measurements: · Volume · pH · Temperature Laboratory analysis: · Suspended Solids · COD · BOD5 · TOC · Ammoniacal–nitrogen · Nitrate-nitrogen · Nitrite–nitrogen · Total Nitrogen · Sulphate · Phosphate · Oil & Grease · Alkalinity · Chloride · Calcium · Potassium · Magnesium · Iron · Zinc · Copper · Chromium · Nickel · Cadmium · Boron
|
1 – 23 Mar 2022 |
TOA HM-30P (S/N: 790332)
|
|
|
|
||
Note: (a) Reduction of monitoring frequency will be subject to the monitoring results to demonstrate environmentally acceptable performance. |
The schedule for leachate monitoring during the reporting period is provided in Annex C.
The leachate levels and effluent quality monitoring results are summarised in Table 2.22 and Table 2.23, respectively. The detailed monitoring results are provided in Annex F5 and Annex F6, respectively.
Table 2.22 Summary of Leachate Levels in the Reporting Period
Monitoring Location |
Average Leachate Head Levels (cm) (Range in Bracket) |
Limit Level (cm) |
Pump Station No. 1X (Cell 1X) |
||
Meter No. X-1 |
57 (42 – 79) |
> 178 |
Meter No. X-2 |
74 (48 – 99) |
|
Average |
66 (52 – 89) |
|
Pump Station No. 2X (Cell 2X) |
||
Meter No. X-3 |
78 (66 – 88) |
> 180 |
Meter No. X-4 |
80 (68 – 90) |
|
Average |
79 (67 – 89) |
|
Pump Station No. 3X (Cell 3X) |
||
Meter No. X-5 |
80 (53 – 168) |
> 175 |
Meter No. X-6 |
80 (53 – 168) |
|
Average |
80 (53 – 168) |
|
Table 2.23 Summary of Effluent Quality Monitoring Results in the Reporting Period
Parameters |
Average Monitoring Results (Range in Bracket) |
Limit Level |
Effluent Discharged from LTP |
||
Temperature |
29.4°C (24.9°C – 32.7°C) |
> 43 °C |
pH Value |
8.4 (8.3– 8.5) |
6 – 10 |
Volume Discharged |
1,059m³ (357m³ - 1,498m³) |
>1,500 m³ |
Suspended Solids (SS) |
23.6mg/L (10.7mg/L – 84.8mg/L) |
> 800 mg/L |
Phosphate |
8.0mg/L (4.4mg/L – 10.4mg/L) |
> 25 mg/L |
Sulphate |
151mg/L (114mg/L – 199mg/L) |
> 900 mg/L |
Total Inorganic Nitrogen (a) |
49.4mg/L (32.8mg/L – 63.3mg/L) |
> 100 mg/L |
BOD |
9mg/L (6mg/L – 13mg/L) |
> 800 mg/L |
COD |
874mg/L (516mg/L – 1,190mg/L) |
> 2,000 mg/L |
Oil & Grease |
<5mg/L (<5mg/L – <5mg/L) |
> 20 mg/L |
Boron |
4,824µg/L (3,560µg/L – 5,570µg/L) |
> 7,000 µg/L |
Iron |
1.24mg/L (0.86mg/L – 1.63mg/L) |
> 7.5 mg/L |
Cadmium |
<1.0µg/L (<1.0µg/L – <1.0µg/L) |
> 1 µg/L |
Chromium |
113µg/L (86µg/L – 143µg/L) |
> 400 µg/L |
Copper |
20µg/L (15µg/L – 23µg/L) |
> 1,000 µg/L |
Nickel |
107µg/L (80µg/L – 130µg/L) |
> 800 µg/L |
Zinc |
75µg/L (46µg/L – 113µg/L) |
> 800 µg/L |
Note: (a) Total Inorganic Nitrogen include Ammoniacal-nitrogen, Nitrite-nitrogen and Nitrate-nitrogen. |
All the leachate levels and effluent quality monitoring results were below the Limit Levels in the reporting period. No action is thus required to be undertaken in accordance with the Event and Action Plan presented in Annex F3.
According to the updated EM&A Manual of the Project with incorporation of the proposed updates under the Amendment Summary approved by EPD on 15 June 2020, groundwater monitoring was carried out at 14 perimeter groundwater monitoring wells (including 3 up-gradient wells and 11 down-gradient wells) (i.e. MWX-1 to MWX-14) to monitor the groundwater quality and level of the perimeter groundwater monitoring wells at monthly interval.
The Limit Levels for groundwater quality is provided in Table 2.24 below.
Table 2.24 Limit Levels for Groundwater Quality
Location |
Limit Levels |
|
Ammoniacal-nitrogen (mg L-1) |
COD (mg L-1) |
|
MWX-1 |
5.00 |
30 |
MWX-2 |
5.00 |
30 |
MWX-3 |
5.00 |
30 |
MWX-4 |
7.63 |
36 |
MWX-5 |
5.00 |
30 |
MWX-6 |
5.00 |
46 |
MWX-7 |
6.55 |
36 |
MWX-8 |
15.85 |
50 |
MWX-9 |
7.30 |
71 |
MWX-10 |
5.00 |
30 |
MWX-11 |
5.00 |
30 |
MWX-12 |
5.00 |
30 |
MWX-13 |
5.00 |
30 |
MWX-14 |
5.00 |
30 |
A bladder pump with Teflon sampling tube and adjustable discharge rates was used for purging and taking of groundwater sample from the monitoring wells. Filtered groundwater samples was collected by connecting a disposable in-line filter system to the tubing of the sampling pump, prior to storage and analysis by ALS Technichem (HK) Pty Ltd. (HOKLAS Registration No. 066).
A portable dip meter with 5mm accuracy was used for measurement of groundwater level at each well. The dip meter have an audio indicator of the water level and was checked before use.
The measurements of pH and electrical conductivity (EC) were undertaken in situ. In situ monitoring instruments in compliance with the specifications listed under Section 4.3.2 of the updated EM&A Manual were used to undertake the groundwater quality monitoring for the Project.
Details of the equipment used and the monitoring locations are summarised in Table 2.25 and illustrated in Figure 2.1, respectively. Copies of the calibration certificates for the equipment are presented in Annex F7.
Table 2.25 Groundwater Monitoring Details
Monitoring Location |
Frequency |
Parameter |
Monitoring Dates |
Equipment |
|
All groundwater monitoring wells (MWX-1 to MWX-14) |
Monthly |
· Water level · pH · EC · COD · BOD5 · TOC · Ammoniacal–nitrogen · Nitrate-nitrogen · Nitrite–nitrogen · TKN · TN · Sulphate · Sulphide · Carbonate · Bicarbonate · Phosphate |
· Chloride · Sodium · Potassium · Calcium · Magnesium · Nickel · Manganese · Chromium · Cadmium · Copper · Lead · Iron · Zinc · Mercury · Boron |
14, 15 Mar 2022 |
YSI Professional DSS (S/N: 17B102764) |
The schedule for surface water quality monitoring during the reporting period is provided in Annex C.
The groundwater quality monitoring results and detailed monitoring results are summarised in Table 2.26 and provided in Annex F8, respectively.
Table 2.26 Summary of Groundwater Monitoring Results in the Reporting Period
Location |
Ammoniacal-nitrogen (mg L-1) |
COD (mg L-1) |
||
Monitoring Results |
Limit Levels |
Monitoring Results |
Limit Levels |
|
MWX-1 |
0.17 |
5.00 |
4 |
30 |
MWX-2 |
0.02 |
5.00 |
<2 |
30 |
MWX-3 |
1.45 |
5.00 |
17 |
30 |
MWX-4 |
5.91 |
7.63 |
38 |
36 |
MWX-5 |
3.8 |
5.00 |
28 |
30 |
MWX-6 |
3.95 |
5.00 |
46 |
46 |
MWX-7 |
6.18 |
6.55 |
11 |
36 |
MWX-8 |
11.8 |
15.85 |
29 |
50 |
MWX-9 |
3.29 |
7.30 |
17 |
71 |
MWX-10 |
0.02 |
5.00 |
9 |
30 |
MWX-11 |
0.06 |
5.00 |
8 |
30 |
MWX-12 |
<0.01 |
5.00 |
5 |
30 |
MWX-13 |
0.11 |
5.00 |
5 |
30 |
MWX-14 |
<0.01 |
5.00 |
3 |
30 |
Limit Level exceedance was recorded for groundwater monitoring in the reporting period and actions in accordance with the Event and Action Plan presented in Annex F3 were undertaken. Investigation of the Limit Levels exceedance was conducted and the investigation report is presented in Annex F9.
Based on the investigation conducted for the monitoring event with potential Limit Levels exceedance with the Contractor and the IEC, the groundwater quality (COD) exceedance at MWX-4 on 15 March 2022 was considered non Project-related. The Contractor was reminded to implement all relevant mitigation measures for the construction and operation works and maintain good site practice. The ET will keep track on the monitoring data and ensure Contractor’s compliance of the environmental requirements.
According to the updated EM&A Manual of the Project, landfill gas monitoring was carried out at the perimeter of the waste boundary (monitoring wells), area between the SENTX Site boundary and the waste boundary (surface emission), occupied on-site building, service voids, utilities pit and manholes in the vicinity of the SENTX (build-up of landfill gas) during the operation/restoration phase.
The Limit Levels for landfill gas monitoring is provided in Table 2.27 below.
Table 2.27 Limit Levels for Landfill Gas Constituents
Parameters |
Monitoring Location |
Limit Level (% (v/v)) |
|
Perimeter Landfill Gas Monitoring Wells (a) |
|
||
Methane & Carbon Dioxide |
|
Methane |
Carbon Dioxide |
|
LFG1 |
1.0 |
3.2 |
|
LFG2 |
1.0 |
4.3 |
|
LFG3 |
1.0 |
6.3 |
|
LFG4 |
1.0 |
7.0 |
|
LFG5 |
1.0 |
3.4 |
|
LFG6 |
1.0 |
9.1 |
|
LFG7 |
1.0 |
1.5 |
|
LFG8 |
12.6 |
2.4 |
|
LFG9 |
2.5 |
1.7 |
|
LFG10 |
3.5 |
1.6 |
|
LFG11 |
3.0 |
2.0 |
|
LFG12 |
13.2 |
1.5 |
|
LFG13 |
22.5 |
2.7 |
|
LFG14 |
5.2 |
1.8 |
|
LFG15 |
18.2 |
2.0 |
|
LFG16 |
1.0 |
2.0 |
|
LFG17 |
17.8 |
2.4 |
|
LFG18 |
2.3 |
2.1 |
|
LFG19 |
6.3 |
3.1 |
|
LFG20 |
1.0 |
4.6 |
|
LFG21 |
1.0 |
4.8 |
|
LFG22 |
1.0 |
4.0 |
|
LFG23 |
1.0 |
10.3 |
|
LFG24 |
1.0 |
4.7 |
|
GP1 |
1.0 |
10.6 |
|
GP2 (shallow) |
1.0 |
11.4 |
|
GP2 (deep) |
1.0 |
10.4 |
|
GP3 (shallow) |
1.0 |
6.9 |
|
GP3 (deep) |
1.0 |
5.6 |
|
GP4 (shallow) |
1.0 |
11.6 |
|
GP4 (deep) |
1.0 |
7.7 |
|
GP5 (shallow) |
1.0 |
10.8 |
|
GP5 (deep) |
1.0 |
7.5 |
|
GP6 |
1.0 |
8.4 |
|
GP7 |
1.0 |
4.5 |
|
GP12 |
1.0 |
2.3 |
|
GP15 |
1.0 |
2.2 |
|
P7 |
1.0 |
2.5 |
|
P8 |
1.0 |
1.7 |
|
P9 |
1.0 |
2.7 |
Service Voids, Utilities Pits and Manholes |
|||
Methane (or flammable gas) |
Service voids, utilities pits and manholes |
1% by volume |
|
Permanent Gas Monitoring System |
|||
Methane (or flammable gas) |
Permanent Gas Monitoring System |
1% by volume (20% LEL) |
|
Notes: (a) Limit Levels established based on the pre-operation phase baseline and additional landfill gas monitoring results in the Pre-operation Baseline Monitoring Report. |
Gas analysers in compliance with the specifications listed under Section 5.4.1 of the updated EM&A Manual were used to monitor the gas parameters at the landfill gas monitoring wells, service voids, utilities pits and manholes. The gas analyser was calibrated by a laboratory accredited under HOKLAS at yearly intervals and checked before use to ensure the validity and accuracy of the results. A portable dip meter was used to monitor the water level in the monitoring wells.
Permanent gas monitoring systems with pre-set alarm levels for methane at 20% lower explosive limit (LEL, equivalent to 1% methane gas (v/v)) were installed and operated in all occupied on-site buildings at SENTX. A central control panel is equipped to alert site personnel when the gas concentration at any detector reaches the alarm level.
The equipment used in the landfill gas monitoring programme is summarised in Table 2.28. The landfill gas monitoring locations for perimeter landfill gas monitoring wells and service voids, utilities and manholes along the Site boundary and within the SENTX site are illustrated in Figure 2.3 and Annex G1, respectively. Copies of the calibration certificates for the equipment are presented in Annex G2.
Table 2.28 Landfill Gas Monitoring Details
Monitoring Location |
Frequency |
Parameter |
Monitoring Dates |
Equipment |
Perimeter landfill gas monitoring wells (LFG1 to LFG24, P7 to P9, GP1 to GP7, GP12 and GP15)
|
Monthly |
Methane Carbon dioxide Oxygen Atmospheric pressure |
8 Mar 2022 |
GA5000 (S/N: G507306) |
Service voids, utilities and manholes along the Site boundary and within the SENTX Site (UU1 to UU28) |
Monthly |
Methane Carbon dioxide Oxygen |
11 Mar 2022 |
GA5000 (S/N: G507306) |
Permanent gas monitoring system in all occupied on-site buildings |
Continuous |
Methane (or flammable gas) by permanent gas monitoring system |
1 – 31 Mar 2022 |
Permanent gas monitoring system |
The schedule for landfill gas monitoring during the reporting period is provided in Annex C.
The landfill gas monitoring results are summarised and provided in Tables 2.29 - 2.30 and Annex G3, respectively.
Table 2.29 Summary of Landfill Gas Monitoring Results at Perimeter LFG Monitoring Wells in the Reporting Period
Location |
Methane (% (v/v)) |
Carbon Dioxide (% (v/v)) |
||
Monitoring Results |
Limit Levels (a) |
Monitoring Results |
Limit Levels (a) |
|
LFG1 |
0.0 |
1.0 |
0.1 |
3.2 |
LFG2 |
0.0 |
1.0 |
0.4 |
4.3 |
LFG3 |
0.0 |
1.0 |
0.0 |
6.3 |
LFG4 |
0.0 |
1.0 |
0.0 |
7.0 |
LFG5 |
0.0 |
1.0 |
0.0 |
3.4 |
LFG6 |
0.0 |
1.0 |
0.0 |
9.1 |
LFG7 |
0.0 |
1.0 |
0.0 |
1.5 |
LFG8 |
0.0 |
12.6 |
0.0 |
2.4 |
LFG9 |
0.0 |
2.5 |
0.0 |
1.7 |
LFG10 |
0.0 |
3.5 |
0.0 |
1.6 |
LFG11 |
0.0 |
3.0 |
0.0 |
2.0 |
LFG12 |
0.0 |
13.2 |
0.0 |
1.5 |
LFG13 |
0.0 |
22.5 |
0.0 |
2.7 |
LFG14 |
0.0 |
5.2 |
0.0 |
1.8 |
LFG15 |
0.0 |
18.2 |
0.0 |
2.0 |
LFG16 |
0.0 |
1.0 |
0.0 |
2.0 |
LFG17 |
0.0 |
17.8 |
0.0 |
2.4 |
LFG18 |
0.0 |
2.3 |
0.1 |
2.1 |
LFG19 |
0.0 |
6.3 |
0.0 |
3.1 |
LFG20 |
0.0 |
1.0 |
0.4 |
4.6 |
LFG21 |
0.0 |
1.0 |
2.0 |
4.8 |
LFG22 |
0.0 |
1.0 |
0.5 |
4.0 |
LFG23 |
0.0 |
1.0 |
1.4 |
10.3 |
LFG24 |
0.0 |
1.0 |
0.8 |
4.7 |
GP1 |
0.0 |
1.0 |
3.1 |
10.6 |
GP2 (shallow) |
0.0 |
1.0 |
0.1 |
11.4 |
GP2 (deep) |
0.0 |
1.0 |
0.1 |
10.4 |
GP3 (shallow) |
0.0 |
1.0 |
3.3 |
6.9 |
GP3 (deep) |
0.0 |
1.0 |
0.1 |
5.6 |
GP4 (shallow) |
0.0 |
1.0 |
0.2 |
11.6 |
GP4 (deep) |
0.0 |
1.0 |
0.1 |
7.7 |
GP5 (shallow) |
0.0 |
1.0 |
0.1 |
10.8 |
GP5 (deep) |
0.0 |
1.0 |
0.1 |
7.5 |
GP6 |
0.0 |
1.0 |
0.4 |
8.4 |
GP7 |
0.0 |
1.0 |
0.1 |
4.5 |
GP12 |
0.0 |
1.0 |
0.6 |
2.3 |
GP15 |
0.0 |
1.0 |
0.0 |
2.2 |
P7 |
0.0 |
1.0 |
0.0 |
2.5 |
P8 |
0.0 |
1.0 |
0.0 |
1.7 |
P9 |
0.0 |
1.0 |
0.0 |
2.7 |
Notes: (a) Limit Levels established based on the pre-operation phase baseline and additional landfill gas monitoring results in the Pre-operation Baseline Monitoring Report. |
Table 2.30 Summary of Landfill Gas Monitoring Results at Service Voids, Utilities Pits and Manholes in the Reporting Period
Location |
Methane (% (v/v)) |
|
Monitoring Results |
Limit Levels |
|
UU01 |
0.0 |
1.0 |
UU02 |
0.0 |
1.0 |
UU03 |
0.1 |
1.0 |
UU04 |
0.1 |
1.0 |
UU05 |
0.0 |
1.0 |
UU06 |
0.0 |
1.0 |
UU07 |
0.3 |
1.0 |
UU08 |
0.0 |
1.0 |
UU09 |
0.0 |
1.0 |
UU10 |
0.0 |
1.0 |
UU11 |
0.0 |
1.0 |
UU12 |
Voided due to latest site programme and on-going operation work |
1.0 |
UU13 |
0.0 |
1.0 |
UU14 |
0.0 |
1.0 |
UU15 |
0.0 |
1.0 |
UU16 |
0.0 |
1.0 |
UU17 |
Voided due to latest site programme and on-going operation work |
1.0 |
UU18 |
0.0 |
1.0 |
UU19 |
0.2 |
1.0 |
UU20 |
0.0 |
1.0 |
UU21 |
0.0 |
1.0 |
UU22 |
0.0 |
1.0 |
UU23 |
0.0 |
1.0 |
UU24 |
0.0 |
1.0 |
UU25 |
0.0 |
1.0 |
UU26 |
0.0 |
1.0 |
UU27 |
0.0 |
1.0 |
UU28 |
0.0 |
1.0 |
The alarm of the permanent gas monitoring systems with pre-set levels for methane at 20% lower explosive limit (LEL, equivalent to 1% methane gas (v/v)) was not triggered at all occupied on-site buildings at SENTX in March 2022.
All the landfill gas monitoring results were below the Limit Levels in the reporting period. No action is thus required to be undertaken in accordance with the Event and Action Plan presented in Annex G4.
According to the updated EM&A Manual of the Project, the monthly landscape and visual audit was conducted on 18 March 2022 to monitor the implementation of the landscape and visual mitigation measures during operation/ restoration phase.
All relevant environmental mitigation measures listed in the approved EIA Report and the updated EM&A Manual and their implementation status are summarised in Annex B.
The Contractor has implemented environmental mitigation measures as stated in the approved EIA Report and the EM&A Manual.
Regarding the landscape and visual audit, the Contractor was reminded to maintain the advance screen planting works regularly to ensure effective screening of views of project works from the High Junk Peak Trail.
Site inspections were carried out on a weekly basis with the Contractor, IEC and ER to monitor the implementation of proper environmental pollution control and mitigation measures under the Project. In the reporting period, 5 site inspections were carried out on 3, 10, 17, 24 and 31 March 2022.
Key observations during the site inspections are summarised in Table 2.31.
Table 2.31 Key Observations Identified during the Site Inspection in this Reporting Month
Inspection Date |
Environmental Observations and Recommendations |
3 March 2022 |
· The Contractor shall remove the general refuse accumulated at the channel near sump house 3 and along Western site boundary and dispose of the waste regularly. · The Contractor shall remove the stagnant water accumulated in the drip tray for generator at Cell 4X. |
10 March 2022 |
· The Contractor shall display a NRMM label on the excavator near RC15. · The Contractor shall remove the general refuse accumulated at the channel near sump house 2 and 3 and dispose of the waste regularly. · The Contractor shall clean up the oil spillage near sump house 4 and handle the clean-up materials as chemical waste. · The Contractor shall provide drip tray for the chemical stored at Cell 4X. |
17 March 2022 |
· The Contractor shall remove the stagnant water accumulated at the channel near pump house 3 regularly, and spray larvicides for mosquito control, if necessary. · The Contractor shall dispose of the waste and remove the stagnant water accumulated at the refuse skip near DP6 regularly to minimise odour and pest issues. |
24 March 2022 |
· The Contractor shall display a NRMM label on the excavator near EPD building. · The Contractor shall clean up the oil spillage at the excavator near pump house 3 and handle the clean-up materials as chemical waste. · The Contractor shall remove the general refuse and stagnant water accumulated near Towngas plant and DP6 and dispose of the waste regularly to minimise odour and pest issues. |
31 March 2022 |
· The Contractor shall remove the stagnant water accumulated at the channel near sump house 3 regularly and spray larvicides for mosquito control, if necessary. · The Contractor shall remove the general refuse and stagnant water accumulated at the refuse skip near DP6 and Towngas plant and dispose of the waste regularly to minimise odour and pest issues. |
The Contractor has rectified all observations identified during environmental site inspections in the reporting period. Key environmental deficiencies identified and the corresponding rectification actions are presented in Table 2.32.
Table 2.32 Summary of Environmental Deficiencies Identified and Corresponding Rectification Actions
Deficiencies |
Rectifications Implemented |
Proposed Additional Control Measures |
Surface Water |
||
Intercepting channels & drainage system |
Reviewed drainage plan. |
Addition of channels. Expedite the construction of permanent sediment trap and discharge culverts.
|
DP channels (design & regular silt removal) |
Carried out regular maintenance and cleaning of channels. DP4 channel: Area near the channel was paved with concrete and a bund was built. DP6 channel: Gravel piles on the channel were covered with concrete which serve as blocks for running water and to divide the channel into several sections. A pump was placed in the water zone in the upstream section to pump water to the Wetsep for treatment prior to the discharge to the last section before the weir plate. DP6: Pipes through the gravel piles between different channel sections were covered with geotextiles to block debris and silt.
|
N.A. |
Stockpiles & exposed soil |
Installed silt fencing near surface water channel along DP6 channel. |
Improve soil covering. Compaction and cover for stockpiles and soil slopes.
|
Wetsep (treatment capacity & number) |
Reviewed Wetsep capacity. Chemicals dosage of the Wetsep was increased to enhance the efficiency. |
Install additional Wetsep. |
Backflow / ponding during heavy rainfall |
Raised with EPD (LDG) and CEDD. |
N.A. |
The Contractor has registered as chemical waste producer under the Contract. Sufficient numbers of receptacles were available for general refuse collection and sorting.
As informed by the Contractor, waste generated during this reporting period include mainly inert C&D materials. Reference has been made to the waste flow table prepared by the Contractor. The quantities of different types of wastes and imported fill materials are summarised in Table 2.33.
Table 2.33 Quantities of Different Waste Generated and Imported Fill Materials
Month/ Year |
Inert C&D Materials (a) (in ‘000m3) |
Imported Fill |
Inert Construction Waste
Re-used |
Non-inert Construction Waste
(c) |
Recyclable Materials (d) (in ‘000kg) |
Chemical Wastes |
|
Rock |
Soil |
||||||
1 – 31 Mar 2022 |
0.039 |
0 |
0 |
0 |
0.010 |
0 |
0.800 |
Notes: (a) Inert construction wastes include hard rock and large broken concrete, and materials disposed as public fill. Density assumption: 1.6 (kg/L) for public fill. (b) Imported fill refers to materials generated from other project for on-site reuse. (c) Non-inert construction wastes include general refuse disposed at landfill. Density assumption: 0.9 (kg/L) for general refuse. (d) Recyclable materials include metals, paper, cardboard, plastics and others. |
A summary of the Environmental Mitigation Implementation Schedule is presented in Annex B. The necessary mitigation measures were implemented properly for the Project.
The operation/ restoration phase air quality, noise and landfill gas monitoring results complied with the Action and Limit Levels in the reporting period. One exceedance of the Limit Level for groundwater (COD) was recorded for water quality impact monitoring in the reporting period. The groundwater (COD) exceedance at MWX-4 on 15 March 2022 was considered non Project-related upon further investigation.
Cumulative statistics on exceedances is provided in Annex H.
There were no complaints, notification of summons or prosecution recorded in the reporting period.
Statistics on complaints, notifications of summons, successful prosecutions are summarised in Annex H.
As informed by the Contractor, the major works for the Project in April 2022 will be:
Excavation and removal of unsuitable fill materials;
Import materials for Cell 4X;
Liner works at Cell 4X;
Construction of perimeter bund along the West side of Cell 4X;
Equipment installation at pump house 4;
Utilities installation along the perimeter channel at Western bund of Cell 4X;
Defects rectification for waste reception area, including weighbridge, vehicle washing facilities, wheel wash bay and guard house;
Defects rectification for infrastructure buildings;
Defects rectification for pavement works at Part X1 area;
Defects rectification for surface water channels along the road pavement;
Installation of the remaining LFG and leachate HDPE pipes at Cell 4X;
Construction of MSE wall;
Road pavement along the crest of Western bund of Cell 4X; and
Landscaping work.
Potential environmental impacts arising from the above upcoming construction activities in the next reporting period of April 2022 are mainly associated with potential surface water impact in the rainy season. The ET will keep track on the construction and operation works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.
The tentative schedule for environmental monitoring in April 2022 are provided in Annex I.
This EM&A Report presents the findings of the EM&A activities undertaken during the period from 1 to 31 March 2022 in accordance with the updated EM&A Manual and the requirements of the Environmental Permit (EP-308/2008/B).
Air quality (24-hour TSP, odour, thermal oxidiser, landfill gas flare and landfill gas generator stack emission), noise, water quality (surface water, leachate and groundwater) and landfill gas monitoring were carried out in the reporting period. Results for air quality, noise and landfill gas monitoring complied with the Action and Limit Levels in the reporting period. One exceedance of the Limit Level for groundwater (COD) was recorded in the reporting period.
Environmental site inspections were carried out during the reporting period. Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site inspections.
There were no complaints, notification of summons or prosecution recorded in the reporting period.
The ET will keep track on the construction and operation/restoration works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.